What is the expected output of a Planning Poker meeting?
The team gave feedback to the Product Owner about the acceptance criteria.
The team made a preliminary plan for which stories will be completed in the next quarter.
The stories were discussed and each had a story point estimate assigned.
The team decided what stories should be developed within the same sprint.