How do you mark a task's progress and have that progress reflected in the task's summary task?
Use the Project Information dialog box.
Use the Task tool en the ribbon's Task tab for the summary task.
Enter a value in the %Complete field.
Use the Task tool on the ribbon's Task tab for the subtask.